With lots of scaffolding on its facade, the new Laguna Niguel City Hall continues its path to completion.

Driving past the new Laguna Niguel City Hall, you might think you were in Europe or downtown New York thanks to all of the scaffolding.

The following is the anticipated construction activity for the week of March 7 - 11:

  •   Continue exterior plaster and final color coat.
  •   Continue installation of roof tiles.
  •   Continue interior drywall.
  •   Begin installation of accent tiles in entry arches and bell tower.
  •   Begin painting the exterior of the building.


Completion is scheduled for late summer.