Crown Valley Widening Moving Along

The project began in July and is expected to be completed by December 2012, city officials say.

In between flashing signs, delays and dust, construction seems to be moving along in the Crown Valley widening projet.

Deputy Public Works Director Nick Renn says the photos show the construction of the reinforced concrete drainage box which is connecting to the existing storm drain pipe and the construction of abutment footings for the bridge widening over the railroad. 

Also shown is a bridge column being constructed between the north and south bound lanes of the I-5 freeway. This is one of the columns that will support the bridge widening over the freeway. 

Find out what's happening in Laguna Niguel-Dana Pointwith free, real-time updates from Patch.

In the next few weeks the contractor will erecting the temporary falsework which is used to build the bridge decks. 

The project is on schedule with construction expected to be completed by December 2012.

Find out what's happening in Laguna Niguel-Dana Pointwith free, real-time updates from Patch.

 

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?