Construction of New City Hall Winding Down

The following construction activities are anticipated for the week of July 18-22.

The City Hall construction project is nearing completion. Finish work in the council chambers and community room, as well as installation of the office furniture, has begun.  

The installation of hardscape, pedestrian amenities and landscaping is also almost finished.

Construction activities are anticipated for the week of July 18-22 include: 

  • Begin delivery and installation of system furniture in second-floor office area.
  • Install flooring in Council Chambers.
  • Continue installation of irrigation system and landscaping of the site.
  • Continue driveway improvements at the entrance drive and other site work.


The new City Hall is scheduled to be open for business the week of Aug. 29.

Find out what's happening in Laguna Niguel-Dana Pointwith free, real-time updates from Patch.

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?